DWR Announces POTENTIAL USE OF LAKE OROVILLE MAIN SPILLWAY NEXT WEEK

  • by California Department of Water Resources
  • Apr 3, 2018
  • Water News

The California Department of Water Resources today released the following statement regarding the use of Lake Oroville’s main spillway.

SACRAMENTO – Forecasted storms expected in the Feather River basin this weekend may require using Lake Oroville’s flood control outlet spillway (also known as the main spillway) this week or next.

After last year’s spillway incident, the Department of Water Resources (DWR) created the 2017/18 Lake Oroville Winter Operations Plan to ensure public safety in the event of major storm events. This plan triggers more aggressive outflow from Hyatt Powerplant and potential use of the main spillway should the reservoir’s elevation reach 830 feet during the month of April. The current forecasts show the potential for inflows to raise the reservoir to near the 830-foot trigger elevation by the middle of next week. Currently, the lake elevation is 794 feet.

In anticipation of the incoming weather, DWR began increasing outflows today, April 3, from Hyatt Powerplant to approximately 10,000 cfs. The total capacity of outflows from Hyatt Powerplant is currently 12,500 cfs. If necessary, DWR also has use of the River Valve Outlet System which has an additional maximum outflow capacity of 4,000 cfs.

DWR’s objective for the year has been to minimize use of the main spillway while it is still under construction. However, because forecasts are uncertain, DWR is taking proactive steps such as early notification to downstream communities, regulatory agencies and construction crews to prepare for possible use of the main spillway next week in the event the lake level reaches an elevation of 830 feet, even after increasing outflows through Hyatt Powerplant.

Phase I of the reconstruction of the main spillway was completed in November 2017 to handle outflows of 100,000 cfs. The design of the partially reconstructed spillway was approved by the Federal Energy Regulatory Commission, Division of Safety of Dams and an Independent Board of Consultants that has been overseeing reconstruction. Phase II of construction on the main spillway will begin in May, depending on weather.

Phase I included repair and replacement of the upper chute and end of the chute with structural concrete, and construction of a temporary roller-compacted concrete (RCC) section in the middle chute. Since the surface finish of the temporary RCC section is not as smooth as the structural concrete sections, the flow may be more turbulent than in the upper chute. Additional wear may also occur to the surface of the temporary RCC. Phase I construction included structural concrete cutoff walls at the connections between the structural sections and RCC section as measures to protect against possible wear of the RCC.

If the main spillway is used, inspectors will be closely monitoring the chute and flows.

DWR has notified the following groups about the increase in outflows and potential use of the spillway:

  • State and federal regulatory agencies
  • Local and statewide public safety organizations, including the Butte County Sheriff’s office
  • Partner state agencies
  • Local, state and federal elected officials
  • Community members and stakeholders

Because the forecasts are dynamic, they could change in magnitude and timing. DWR will provide regular communication to the community, stakeholders and the media about forecasts and their impact to Oroville operations over the coming days as the storms approach.

Suggested Resources

15 RESOURCES prev next
2018 ACWA Member Directory

Sorry, but only ACWA members have permission to view this content. Member login is required.

Federal Regulatory Chart

Sorry, but only ACWA members have permission to view this content. Member login is required.

Joint Comments on Proposed Recycled Water Policy Amendment

Sorry, but only ACWA members have permission to view this content. Member login is required.

Long-Term Conservation Resources (SB 606/AB 1668)

Sorry, but only ACWA members have permission to view this content. Member login is required.

ACWA Statewide Reservoirs Mercury Control Program Technical Presentations Webinar

On May 30, 2018 ACWA hosted the Statewide Reservoirs Mercury Control Program Technical Presentations. This webinar highlighted state and local […]

Priority Issues Bulletin

Sorry, but only ACWA members have permission to view this content. Member login is required.

Joint Comments on State Water Board Electronic Annual Reporting

Submitted to the State Water Resources Control Board on May 30, 2018.

Comments on U.S. EPA Clean Water Act Coverage of “Discharges of Pollutants”

Submitted to the U.S. Environmental Protection Agency on May 21, 2018.

ACWA 2018 Spring Conference Presentations

Presentations from ACWA’s 2018 Spring Conference & Exhibition held May 8-11 in Sacramento are available below. Please note that this […]

Joint Comments on the U.S. Forest Service’s Fiscal Year 2019 Budget

Submitted to U.S. Senators Lisa Murkoski and Maria Cantwell, Senate Committee on Energy & Natural Resources on May 8, 2018.

ACWA’S 2018 Spring LEGAL AFFAIRS COMMITTEE CLE WORKSHOP MATERIALS

The following presentations and materials for ACWA’s 2018 Legal Affairs Committee CLE Workshop on May 8 from 9 a.m. to […]

2017 Year in Review

During 2017, ACWA and its membership proved how strength through collaboration can achieve goals unprecedented in terms of complexity and […]

No Water Tax Toolkit

Sorry, but only ACWA members have permission to view this content. Member login is required.

2017 Summary of Legislation

ACWA’s 2017 Summary of Legislation provides concise information on legislation enacted in the first year of the 2017-’18 legislative session that […]

2017 Summary of Appellate Cases

ACWA’s  2017 Summary of Appellate Cases details court decisions in 2016-’17 that may be of interest to ACWA member agencies […]

Suggested News

15 Articles prev next
ACWA News: July 20, 2018

Sorry, but only ACWA members have permission to view this content. Member login is required.

Water Wins in D.C. Underway

Despite increasing polarization in our nation’s capital, significant progress is being made on several issues of importance to ACWA members. As […]

Faces of Water Q&A – July 2018

1. Describe your job. My job is to ensure the financial health and integrity of San Juan Water District on […]

Member Spotlight – July 2018

100-year-old Alpine Dam Underpins Marin Municipal Water District’s Rich History Replacing pipelines, maintaining infrastructure and ensuring the flow of high-quality […]

RCWD will install nine new water bottle fill stations at local schools

Temecula, Calif. – To promote tap water while reducing waste, Rancho California Water District (RCWD/District) is installing water bottle fill […]

EMWD Receives Grant Funding from Bureau of Reclamation

Perris, Calif. — Eastern Municipal Water District (EMWD) was recently awarded $750,000 in grant funding from the United States Bureau […]

Yuba County Water Agency rebrands as Yuba Water Agency, unveils new logo

Marysville, Calif. —  Yuba County Water Agency announced today that it is rebranding as Yuba Water Agency, to provide a simple, […]

State Plan to Improve Delta Conditions Further Refined to Reduce Impacts

The California Department of Water Resources (DWR) on Tuesday released a Draft Supplemental Environmental Impact Report/Environmental Impact Statement (EIR/EIS) for […]

Tour Mesa Water’s Water-Wise Garden at the Orange County Fair, Free with Fair Admission

Take a guided tour of Mesa Water District’s water-wise demonstration garden during the 2018 Orange County Fair to learn about beautifying […]

ACWA To Host Webinar on New Long-Term Water Use Efficiency Laws

ACWA will host a webinar from 11 a.m. to noon on July 25 to discuss the new long-term water use […]

JULY PRIORITY ISSUES UPDATE AVAILABLE TO MEMBERS

The July 2018 Priority Issues Update is now available online to members. The update is bullet-style summary of the latest […]

2018 Member Directory Now Available

ACWA’s 2018 Member Directory is now available for online viewing and downloading by public agency members and associates. The directory […]

House Passes Reclamation Title Transfer and Non-Federal Infrastructure Incentivization Act

On Thursday, the House of Representatives passed HR 3281, the “Reclamation Title Transfer and Non-Federal Infrastructure Incentivization Act” by a […]

EMWD Receives $2.78M in U.S. Army Corps of Engineers Workplan

Perris, Calif. — Eastern Municipal Water District (EMWD) has received a funding appropriation of $2.78 million from the United States […]

ACWA Statement on Release of Draft Final Bay-Delta Plan Update For The Lower San Joaquin River and Southern Delta

Sacramento – Timothy Quinn, executive director of the statewide Association of California Water Agencies (ACWA), issued the following statement today in […]